Following protracted negotiations with various suppliers Kit Buildings Direct came out on top both on price and ease of construction. Having placed the order a year ago we took delivery of the whole kit within three months whilst it took six months to find a contractor to erect. The contractor put up the frame in ten days and started cladding before going into liquidation, fortunately the instructions provided by Kit Buildings enabled our volunteers to complete the task over the next few months. We are very pleased with the building, none of the delays or challenges were down to Kit Buildings who have been helpful and understanding through out. Final outcome – a successful new tram depot where we are now installing tracks and concrete floor.
Ian Reed 3rd January 2023